Work on an 80 kilometre repair and replacement project on the PNG Western Transmission Gas line from Salvus to Galloway near Port Edward will get underway later this year, with PNG announcing that the British Columbia Utilities Commission has approved their proposed project.
The project is expected to take three years to complete, with the new line to be in service sometime in 2023. As it moves across Northwestern BC, it is expected to generate up to 250 direct and indirect jobs across the region.
In their statement, (which you can review here) PNG notes that environmental concerns will be an integral part of the work ahead over the next three years.
Work will be completed under the guidance of trained environmental specialists, archeologists and Indigenous environmental monitors to minimize impacts to fish and wildlife, the habitat, cultural values and environmentally sensitive and protected areas.
The company has also promised to continue on with its communication efforts with Indigenous communities, local governments and the general public as the timetable for the project moves forward.
The BCUC decision of July 8th granting the Application for a Certificate of Public Convenience and Necessity for the Salvus to Galloway Gas Line Upgrade Project can be examined here.
The documentation that was included as part of the PNG application to the commission can be reviewed here.
More notes related to the work of PNG in the Northwest can be reviewed from our archive page.