Monday, April 25, 2022

Progress for City's ongoing Water infrastructure rebuild with twin calls for Bids from City of Prince Rupert

A diagram as part of the Bid Package for the City's plans for the 
ongoing water infrastructure work that is underway
(From BC Bid website)

Two more elements of development of the city' s water infrastructure have been put out for Bid with the provincial BC Bid website, with the City of Prince Rupert putting both the Fern Passage Submarine Water Main Design and the Shawatlans Water Main and Overland Works bids both published on Friday.

The twin calls for proposals are being handled by Colliers Project Leaders for the City, the deadlines for submissions of interest are staggered between May 6th and 13th.

The Background related to the Fern Passage Submarine Water Main Design can be reviewed below:

click to enlarge

The schedule for development of that project is listed below:


Proposed improvements for overland waterline replacement
(from BC Bid package)

The background for the Shawatlan Lake Connection looks as follows:

click to enlarge

The Schedule towards that element of the RFP is outlined below:


The full documentation towards the twin Bids can be reviewed from the BC Bid website here.

Operations Director Richard Pucci noted earlier this month that the Bid process for both was set to launch as part of his Major projects Update for Council at their April 11th Council Session.

Our archive to items related to past Bids and Awards from the City can be found here.

More notes on the range of Major Projects and Infrastructure underway can be explored here.


No comments:

Post a Comment