Friday, September 14, 2012

Council calls on Port Authority to explain Pinnacle Pellet approval

In a motion introduced into the September 4th session, Prince Rupert City Council has instructed staff to invite members of the Prince Rupert Port Authority to attend council session to explain its recent approval of the Pinnacle Pellet project.

The motion introduced by Councillor Joy Thorkelson who was referencing the recent Port of Prince Rupert press release (see  1:45.20 mark of council recording) will seek to learn more about the project, which was given approval by the Port last week.

The Pinnacle Pellet project has been a contentious issue for council which has heard numerous concerns from residents in the Water Street and Graham Avenue areas, expressing their fears over such a large scale development on the city's west side waterfront.

The Pinnacle Pellet Project will see a storage and shipment terminal built along the waterfront near where the old Prince Rupert Grain Elevator once stood in the 1980's.

Residents of the area, many of whom probably never had to deal with a working Industrial waterfront in that area other than the freight yard, have been trying to stop the project since it was first brought up earlier this year.

Council has weighed in from time to time on the issue, but they are no doubt more than aware that there may be little they could offer up to stop such a development even if they wanted to and thus far council members haven't been forced to make a stand yea or nay on the subject.

The process moves to the front of the line now as the Port issues it's approval notice having conducted its reviews and made what it hopes are arrangements to stem the concern of the residents of the region.

It is no doubt to those points that council will seek more information whenever the Port appears at council session, from there it will be interesting to see how the six councillors and the Mayor move from that session.

Industrial Devleopment -- Pinnacle Pellet Plant

Sunday, September 2, 2012

Pinnacle Pellet Plant Project clears a hurdle

"PRPA acknowledges the feedback and concerns expressed by some local residents regarding land use management in the inner harbour adjacent to CN's downtown railyard,... However, we believe we can strike a balance between creating the economic opportunity a growing port represents and enhancing the livability of Prince Rupert through improvements to public access to the waterfront."--The Port of Prince Rupert's Director of Public Affairs Ken Veldman, outlining the Port's position on moving forward with the Pinnacle Pellet Plant proposal.

The Pinnacle Pellet Plant, the much discussed project for Prince Rupert's waterfront has cleared its first major hurdle, with the announcement last week that the Prince Rupert Port Authority had approved the Westview Terminal Redevelopment Project.

Better known to Rupertites as the Pinnacle Pellet Plant Project, the Renewable Energy company based out of Quesnel will create a storage and shipment facility at the old Westview Grain Elevator site on Prince Rupert's waterfront, located midway between the current container port and the Kwinitsa Station/Waterfront Park area.

The proposal, galvanized a segment of West side residents who expressed their opposition to the plans both to the Port and the City of Prince Rupert, through petitions, a website and appearances at public functions.

The Port Authority made a nod towards those concerns in their press release of Friday.

However by their announcement moving the project forward, the Port it would seem feels that they have addressed those issues, publishing the findings of the environmental assessment to their website for further examination.

Among the recommendations of the environmental assessment were commitments to Air Quality and Noise, with conditions and remediation to be put in place governing those two key issues of concern.

Air Quality: Pinnacle will be required to carry out continuous air quality monitoring by qualified environmental monitors throughout construction, operation and potential decommissioning of the project. Pinnacle will work with the BC Ministry of Environment to develop a plan that will achieve the required monitoring, ensure adherence to current regulatory standards, and determine corrective steps to be taken in the event that limits are exceeded.

 Noise: Pinnacle will be required to carry out continuous noise monitoring during terminal operations. Furthermore a plan will be designed to confirm the accuracy of the Baseline Noise Assessment, confirm that the proposed noise mitigation measures are effective, and determine corrective steps to be taken in the event that limits are exceeded.

Upon completion, the Terminal will have represented a capital investment estimated at 42 million dollars in the Prince Rupert region, provide for over 90,000 hours of construction work and created up to 24 new direct jobs in terminal operations, as well as contribute to the municipal tax base.

Previous Items from the North Coast Review:

July 14, 2012-- Pinnacle Pellet Plant plans move forward slowly

Other items on the latest developments:

Northern View-- Pellet terminal will be constantly monitored, residents and City need convincing
Northern View-- Pinnacle Pellet Terminal proposed for Prince Rupert receives approval
Globe and Mail-- B. C. Port authority approves terminal for wood pellet exports
Woodworking Network-- Wood Pellet Firm to Invest $42 M on Export Terminal