Monday, February 28, 2022

City Council to review contract award proposals for RCMP project

The first steps towards a new RCMP detachment in the city could be approved this evening, with the City's Chief Financial Officer providing a report that will recommend the awarding of two contracts towards the early stages of the project development.

In her report to Council, the City's CFO Corinne Bomben will recommend that the city Award the Cost Consulting Contract to the BTY Group, while if approved by Council, the Commissioning Contract recommendation will go towards a bid from CES Engineering Ltd.

The two contracts were put out for bid at the end of January, and as Ms. Bomben's report notes six proposals were received for the Cost Consultant competition, three for the Commissioning competition, none of the nine were from local sources.

The BTY Group contract will be set at $48.030 plus GST, while the CES Engineering Ltd. bid comes in at $!28,097.50

Of note from the Bid process is this explanation as to how the city plans to address budget overages from the twin bids.

The fee proposed by BTY is $12,000 below the estimated budget for these services. The fee proposed by C.E.S. is $28,000 over the estimated budget for these services. The high ratings of C.E.S. amongst all evaluators prompted the recommendation from the evaluation team given the quality of the expected service. Overall, combining the two, the overage is $16,000 for these two service components of the project. Efforts will be made to absorb this overage through other project line items and contingency.

The Full report can be reviewed below:


More notes on tonight's Council Session can be explored here.

Some past notes on the plans ahead for the RCMP detachment build can be reviewed from our archive page.

No comments:

Post a Comment