March 1 -- Activists say they drilled holes in CGL pipeline, sabotaged materials
February
February
February 28 -- Coastal GasLink responds to online threat (audio)
February 27 -- 'Trend of escalating violence': Coastal GasLink decries pipeline sabotage claims on anarchist site
February 27 -- Coastal GasLink Investigating Anonymous Online Claim of coordinated sabotage along their pipeline route
February 27 -- BC MLA speaks out publicly against anonymous online threat to sabotage Coastal GasLink pipeline
February 18 -- Energy companies sign up with First National LNG Alliance
February 15 -- LNG Canada and Fortis BC Leave Canadian LNG Allianz in favour of First Nations LNG Alliance
January
January 27 -- Coastal GasLink pipeline project now 83% complete overall, construction nearing 80%
Note: Shell purchased BG Gas in April of 2015, merging the two international giants under the Shell Banner. Petronas signed on as a partner for the Kitimat project in June of 2018.
Archive of items from 2022
Archive of items from 2021
Archive of items from 2020
Archive of items from 2019
Archive of items from 2018
Archive of items from 2017
Archive of items from 2016
Archive of items from 2015
Archive of items from 2014
Archive of items from 2012 and 2013
To return to the most recent blog posting of the day, click here
February 15 -- LNG Canada to begin work to reverse 70 year old alterations to Sumgas Creek, Restoring it to its Natural State
February 14 -- TC Energy 'confident' it will complete $14.5 billion Coastal GasLink pipeline by years' end
February 2 -- Cost of LNG pipeline to Kitimat increases (video)
February 2 -- CGL accusations (video)
January
January 27 -- Coastal GasLink pipeline project now 83% complete overall, construction nearing 80%
January 26 -- Coastal Gas Link fined again (video)
January 26 -- LNG Canada, BC Hydro explore electrification options
January 25 -- Third fine issued to Coastal GasLink project
January 25 -- Coastal GasLink receives third fine for failure to adequately control sediment and erosion along their pipeline route
January 24 -- Coastal GasLink investigation (video)
January 23 -- Forte back in Prince Rupert Harbour for staging before trip to Kitimat and LNG Canada unloading NCR
January 20 -- LNG Canada eyes electrification as planned expansion would send BC emissions skyrocketing
January 19 -- RCMP, Coastal GasLink deny conspiring with private security firm to intimidate Wet'suwet'en protesters
January 18 -- Lack of Electrical Infrastructure may force LNG Canada's proposed second phase to use Natural Gas for Power
January 17 -- Natural gas, not electricity, to power Canada's first LNG plant, increasing carbon footprint
January 17 -- Regulators probe complaint about sediment flow at CGL pipeline river crossing in Northwest BC
January 16 -- Electricity constraints force BC's first LNG terminal to delay renewable shift
January 16 -- Electricity constraints force BC's first LNG terminal to delay renewable shift
January 6 -- Kitimat work lodge management company found guilty of not properly investigating bullying
January 4 -- Coastal GasLink pipeline more than 80% complete
Note: Shell purchased BG Gas in April of 2015, merging the two international giants under the Shell Banner. Petronas signed on as a partner for the Kitimat project in June of 2018.
Archive of items from 2022
Archive of items from 2021
Archive of items from 2020
Archive of items from 2019
Archive of items from 2018
Archive of items from 2017
Archive of items from 2016
Archive of items from 2015
Archive of items from 2014
Archive of items from 2012 and 2013
To return to the most recent blog posting of the day, click here
No comments:
Post a Comment