An update towards the timeline of a municipal works project from the District of Port Edward has provided a look at how the renovations for the Port Edward Fire Hall will come along.
Work began in early January with the setup stage and prep work getting underway.
As workers head into February the stripping of the Stucco should be nearing completion.
Still to come new concrete footings work on a retaining wall, the main element of the replacement of windows and flashing comes in mid February
Much of the work should be completed by Mid March
The roofing elements will come towards the end of March and early April
A chart provided by the District provides the scope of what's ahead for the project.
click on image to enlarge |
Noting at the time how maintenance work on the facility by the District had fallen behind in recent years.